top of page

Using Acrel Meter Data to Compare Production Shifts and Output

2 days ago
9 min read

A factory can make the same number of parts on two shifts and still use very different amounts of electricity. That gap is where useful questions start. Did one shift run longer? Was a compressor left on during a break? Did a machine spend too much time idling? Was product mix different?


Monthly utility bills cannot answer those questions. They show the total, not the pattern. To compare shifts fairly, electricity records need to sit beside two other records: operating hours and production output. Acrel meters can supply the electrical side of that picture, while equipment supplied by ProSense Instruments can help make the data available to operators, maintenance teams, and production managers.


Wide-angle view of an industrial electrical panel with energy meters and current transformers installed.
Shift comparisons start with reliable metering at the right point in the plant.

Why shift-level electricity data is more useful than the monthly bill


The utility bill is useful for cost control, but it is too broad for production analysis. It usually covers the whole site, all loads, all shifts, and all non-production use. That makes it hard to connect energy use to what happened on the floor.


Shift-level metering gives a clearer view. It can show:


  • How much energy a line used during each shift

  • Whether peak demand happened during start-up, production, or cleaning

  • How much power equipment used while it was supposed to be idle

  • Whether a process used more energy per unit than normal

  • Whether changes in staffing, product type, or setup time affected energy use


The aim is not to turn energy data into a blame tool. A fair comparison needs context. A night shift making a heavier product may use more electricity for valid reasons. A day shift with several changeovers may use more energy per unit because the line was not running steadily. Meter data becomes useful when it helps explain the difference, not when it is viewed on its own.


A good shift comparison normally needs three records lined up by time:


Record

What it shows

Typical source

Electricity use

kWh, demand, current, voltage, power factor

Acrel meter

Operating time

When a line or machine was ready, running, stopped, or idle

PLC, run signal, relay, input module, machine controller

Production output

Units made, batches completed, weight processed, or rejects

Counter, PLC, MES, operator entry, batch record


When these records share the same shift times, the plant can compare performance in a way that is much more useful than looking at energy alone.


Start by deciding what you want to compare


Meter selection should start with the question the data needs to answer. A main incomer meter, a line-level meter, and a machine-level meter all tell different stories.


A site-level meter can show total demand and confirm whether the whole plant is moving in the right direction. It will not show whether Line 2 used too much energy during the late shift.


A distribution-board meter can separate one area from another. That suits plants with several lines, departments, or utility loads such as compressed air, chilled water, or extraction.


A machine-level meter gives the most detail. It is useful for high-energy assets, bottleneck equipment, or machines where idle running is common. It also helps when the same product can run on different machines and the team wants a fair comparison.


Before choosing the meter, define the comparison level:


Comparison goal

Best metering point

Useful result

Compare total plant energy by shift

Main incomer or sub-main

kWh and peak demand for each shift

Compare production lines

Feeder to each line

kWh per line, per shift, per unit

Compare a high-energy machine

Feeder to the machine

Idle load, running load, kWh per cycle

Compare utilities against production

Compressor, pump, chiller, extraction fan

Energy use per operating hour or per output unit

Check electrical quality issues

Board or machine with sensitive drives

Voltage, current balance, power factor, events where available


This step avoids a common mistake: installing a meter where it is easy rather than where it answers the production question.


Close-up view of current transformers clipped around power cables inside a factory panel.
Current transformers let suitable meters measure larger loads safely and accurately.

Choose Acrel meters around load type, data needs, and access method


Acrel offers metering options for different electrical panels and machine loads. The right choice depends on the supply, the current rating, the installation space, and the type of data needed.


For a small single-phase load, a compact DIN rail energy meter may be enough. For a three-phase machine or distribution board, a multi-function meter with current transformer inputs is often more suitable. For a high-value process or a load with drives and motors, it may help to collect more than simple kWh.


The key features to check are practical ones.


Supply type and load size


Confirm whether the load is single-phase or three-phase. Check the supply voltage, maximum current, and whether the installation needs direct connection or CT measurement. Larger loads normally use CTs so the meter can measure current without carrying the full load.


Data points


At minimum, shift analysis needs cumulative kWh. For better diagnosis, collect power, current, voltage, power factor, and sometimes frequency. Demand values are useful when tariffs or electrical capacity matter.


Communication


For regular reporting, choose a meter with a communication output that matches the site system. Common options include RS-485 with Modbus RTU, pulse output, or connection through a gateway. Ethernet or cloud-connected arrangements may suit some sites, depending on the wider equipment package.


Panel format


DIN rail meters suit control panels and distribution boards with rail space. Panel-mounted meters suit switchboards where operators need to see values locally. The physical choice matters because a difficult installation often leads to poor maintenance later.


Inputs and alarms


Some metering arrangements can accept status signals or provide alarm outputs. That can help connect energy records with run signals, trip states, or demand warnings. The exact feature set depends on the chosen model, so it should be checked before ordering.


ProSense Instruments can help match the Acrel meter choice to the site architecture, especially where the meter needs to feed data into a gateway, PLC, display, or reporting system. That matters because the meter is only one part of the measurement chain. The data still has to reach the place where people will use it.


Access the data in a form that production teams can use


Installing a meter is the easy part. The value comes from collecting the readings regularly and storing them with the right time stamps.


A practical setup might use Acrel meters connected over RS-485 to a data logger, gateway, PLC, or monitoring device supplied by ProSense Instruments. From there, the data can be displayed locally, passed to a supervisory system, exported for reports, or stored for later analysis.


The exact path depends on the site, but the principle is the same:


  1. The meter records electrical values.

  2. A connected device reads those values at set intervals.

  3. The system stores the readings with date and time.

  4. Shift times and production totals are added from the production record.

  5. Reports calculate the values that matter.


For shift comparison, the polling interval does not always need to be extremely fast. A one-minute or five-minute record may be enough for kWh, demand trends, and operating patterns. Faster sampling may be useful for short machine cycles or fault diagnosis, but it creates more data to store and manage.


Accuracy also depends on time alignment. If the production counter closes at 14:00 but the meter record is taken at 14:05, the comparison will drift. The shift boundary should be clear and consistent. Where possible, use the same clock source for the meter-reading equipment, production system, and reporting tool.


Eye-level view of a technician checking a local energy display beside a production machine.
Useful shift reports depend on meter readings that operators and engineers can access.

Turn raw readings into fair shift comparisons


Raw kWh totals are a good start, but they do not tell the full story. A shift that ran for eight hours will usually use more energy than a shift that ran for six. A shift that made more output may use more energy while still performing better.


The basic calculation is simple:


`Shift kWh = meter reading at shift end - meter reading at shift start`


From there, compare energy against time and output.


Measure

Calculation

What it tells you

kWh per shift

End kWh minus start kWh

Total electricity used during the shift

kWh per operating hour

Shift kWh divided by run hours

Energy intensity while equipment was available or running

kWh per unit

Shift kWh divided by good output

Energy cost of production output

Idle kWh

Power used during non-production periods

Waste from equipment left running

Peak demand

Highest demand during the shift

Capacity pressure and possible tariff impact


The most useful number is often kWh per good unit. It links electricity use to actual output and reduces the risk of penalising a shift just because it produced more.


Still, use it carefully. Scrap, rework, warm-up time, cleaning, and product mix can all affect the result. A short production run after a cold start may show poor kWh per unit because the machine used energy before saleable output began. That does not mean the shift performed badly. It means the report should show start-up, run time, and output together.


A good shift report might include:


  • Start and end meter readings

  • Total kWh

  • Run hours

  • Planned stop time

  • Unplanned stop time

  • Good units or good weight

  • Rejects or rework

  • kWh per good unit

  • Peak demand

  • Notes on product type or changeovers


The notes matter. A number without context can send the team in the wrong direction.


Look for patterns that point to real problems


Once the same report is produced shift after shift, patterns appear. Some are simple. Others need a closer look.


A machine may show a high base load during breaks. That can mean heaters, pumps, conveyors, extraction, or hydraulics remain on when production has stopped. If the process allows safe shutdown or standby, that becomes a clear saving opportunity.


A line may show similar kWh per hour across shifts but different kWh per unit. That points toward production rate, downtime, or rejects rather than electrical efficiency. The energy system is doing the same work per hour, but the line is producing less saleable output.


A compressor may show heavy energy use on all shifts, even when production is low. That can suggest air leaks, poor pressure control, or machines using air when idle. Metering the compressor feeder and comparing it with operating hours can help confirm whether compressed air use follows production or sits high all the time.


A high peak at the start of every shift may point to equipment starting together. Staggering start-up can reduce demand peaks if the process allows it. This needs care, since production readiness and safety come first.


The point is to use the data as a guide for questions:


  • Which loads stay on during stops?

  • Which shift has the highest kWh per unit after adjusting for product mix?

  • Does demand peak during start-up, steady production, or cleaning?

  • Do utility loads rise and fall with output?

  • Does maintenance work reduce energy use after a repair?


These questions turn meter readings into practical plant knowledge.


Overhead view of a printed shift energy report beside production tally sheets on a workshop bench.
The best comparisons place energy readings next to operating hours and output totals.

Keep the measurement setup reliable


A shift comparison system does not need to be complicated, but it does need discipline. Small errors can create misleading results.


CT orientation is one example. If current transformers face the wrong way, readings may be wrong or confusing. CT ratios must match the meter settings. Phase order and voltage references should be checked during commissioning.


Meter names also matter. A report labelled “Line 1” is only useful if everyone knows exactly what Line 1 includes. If the feeder also supplies lighting, extraction, or a shared conveyor, the report should say so.


Use a simple metering register that records:


  • Meter name

  • Location

  • Load or feeder measured

  • CT ratio

  • Communication address

  • Data points collected

  • Installation date

  • Notes on shared loads


Access rights should also be clear. Operators may need local display values. Engineers may need detailed electrical data. Managers may only need shift summaries. ProSense Instruments supplied equipment can support different access paths, depending on the selected devices and site system.


The reporting process should stay consistent. If one week uses planned shift hours and the next week uses actual run hours, the trend will be hard to trust. Pick definitions and keep them stable.


Build the comparison in stages


The best starting point is usually one important line or utility load, not the entire site. Choose an area where energy cost is meaningful and output data already exists. Install the correct Acrel meter, connect it through the chosen ProSense Instruments supplied equipment, and run reports for a few weeks.


During the first stage, focus on data quality rather than savings. Check whether readings match expectations. Compare meter totals with known operating patterns. Confirm shift boundaries. Ask operators whether the report reflects what happened on the floor.


Once the data is trusted, add more loads or more detail. A staged approach keeps the project manageable and helps the site learn what information is actually useful.


A strong setup will answer three questions every shift:


  1. How much electricity did the process use?

  2. How long did it run or sit idle?

  3. How much good output did it produce?


When those answers sit side by side, energy performance becomes visible. The plant can see whether a high bill came from more production, longer running hours, idle equipment, or a process problem that needs attention.


Acrel meter data is most powerful when it is connected to the real rhythm of production. Select the meter for the load, collect the readings through suitable equipment, align the records with operating hours and output, and use the results to ask better questions. That is how shift comparisons move from rough opinion to reliable evidence.


Comments


bottom of page